基础验收
与土建单位进行工序交接:检验土建基础质量,根据土建单位给定的原始标高和中心线,对轨道基础标高、中心线进行复测,复查结合器预埋外露长度是否与图纸一致。检查结合器内部是否有泥沙等异物,螺栓拧入是否自如。
以上检查项目合格后方可接收,进行轨道安装。否则,不予接收,请土建单位处理好后,再次复验合格,才准接收。
设备验收
轨道垫板、轨道压板、T型螺栓、木螺钉等被列入设备,设备进场后,要检查其出厂合格证、产品外观质量等,检验合格后,与焦化设备部交接,接收,到监理部报验。
材料验收
起重机钢轨QU120、木轨枕等属于材料供应,其中钢轨由首钢京唐供应,木轨枕由中冶京唐自采。材料进场后,也要检查其出厂合格证、产品外观质量等,检验合格后,摆放整齐,木轨枕用塑料布盖好,然后到监理部报验。
目 录
1、工程概况············································2
2、施工部署············································3
3、施工方法············································4
4、轨道接头焊接方法······································5
5、质量控制············································6
6、安全文明施工········································8
7、雨季施工措施·······································11
8、网络进度计划·······································11