钢结构篮球馆施工组织设计
  • 资料等级:
  • 授权方式:资料共享
  • v发布时间:2016-10-13
  • 资料类型:RAR
  • 资料大小:58.2 KB
  • 资料分类:结构设计
  • 运行环境:WinXp,Win2003,WinVista,Win ;
  • 解压密码:civilcn.com
该工程为室内篮球馆,檐口标高为10.5m,建筑面积为1260M2,结构使用年限50年,抗震设防重要性为丙类,设防烈度为7度,设计基本地震加速度0.15g,设计地震分组为第二组,场地类别为Ⅱ类,地面粗糙度B类,结构安全等级二级,耐火等级为二级,地基基础设计等级丙级,砌体施工质量控制等级为B级。主钢构梁柱钢材选用Q235B钢,屋面板采用75mm厚950型EPS夹心板,外板为蓝色,内板为白色。标高1.2000m以下为砖墙,标高1.2000m以上墙体采用双层Q90型单板夹50mm厚保温棉,内板0.4mm,外板0.5mm,内外板均为白色。
目 录
1 施工组织设计编制说明与工程概况···········································12
1.1施工组织设计编制原则和依据···········································12
1.2工程概况·························································12
1.3工期目标·······················································13
1.4工程质量目标··················································13
1.5安全目标·····················································13
1.6文明施工目标··················································13
2 工程进度计划及材料供应········································14
2.1主要用材·····················································14
2.2工程进度计划安排·····················································14
2.3材料供应计划·····················································14
3施工组织管理···························································15
3.1项目管理组织机构和主要施工管理人员配置·······························15
3.2施工管理准备工作·····················································16
3.3施工队伍进场筹备工作·················································17
3.4劳动力配置·················································17
3.5机械设备配置·················································17
4主要施工方法·······················································18
4.1土建施工·················································18
4.2构件的预制和运输·················································18
4.3钢结构安装·················································24
4.4油漆、防火涂料的施工·················································26
4.5彩钢板安装·················································26
4.6其他工程·················································26
5施工过程管理·······························································27
5.1流水作业施工·················································27
5.2物资采购供应·················································27
5.3做好施工过程的协调配合工作···········································28
5.4做好服务工作措施·················································29
5.5做好工程资料管理措施·················································29
6工期、质量、安全、环保、文明施工等保证措施·····································29
6.1工期保证措施·················································29
6.2质量保证措施·················································29
6.3安全生产保证措施············································32
6.4文明施工管理措施·················································33
6.5环保管理措施·················································33
6.6安全防火管理措施············································33
6.7现场临时施工用电管理措施·············································34
6.8工程节约措施·················································35